Updated 12-22-08 Trim
|
|
|
|
Updated 11/11/08
|
|
|
|
|
|
|
|
|
|
|
Updated 10/26/08
Solar installation by Bauer Power |
|
|
|
Stained concrete main floors!
|
|
|
|
|
Passive solar with the concrete main floors for thermal mass!
|
|
|
|
Re-inforced slab with radiant heat tubing in it for heat.
|
|
|
|
|
Concrete is stained in the concrete truck
|
|
|
|
|
|
|
|
Cedar porch
|
|
|
|
updated 9-12-08 Pouring the basement floor.
|
|
|
|
Colored concrete
|
|
|
|
|
|
Updated 8/27/08-Siding is on!
|
|
|
|
|
Installing in-floor heat tubing
|
|
|
|
A walk to remember- Updated 7/24/08
We got an incredible amount of work done this week! |
|
|
|
|
On site chef. I believe that the crew works better when well fed. Here is one of our cooks.
|
|
|
|
This week was a blur, we hit 48 hours by Thursday night, so we loaded up our crews and got them home.
|
|
|
|
These pics will flow from completion backwards.
|
|
|
|
Roof being covered.
|
|
|
|
|
|
Looking at the project from the SkyTrack
|
|
|
|
Framing and sheathing
|
|
|
|
Finished setting trusses
|
|
|
|
Crane setting trusses.
You never know who is going to show up when you rent a crane out of town. We lucked out and set all the trusses in just over an hour!! |
|
|
|
Setting a girder and mono trusses with the SkyTrack.
|
|
|
|
|
This weeks update is brought to you by Team Hybrid.
|
|
|
|
|
We built all of the interior walls
|
|
|
|
John hands a truss up to John.
|
|
|
|
Jeff readys the top plate so the girder truss would sit in the proper place.
|
|
|
|
|
|
|
Garage going up.
|
|
|
|
Laying out walls.- Updated 7/03/08
|
|
|
|
|
|
|
Setting floor joists.
|
|
|
|
Waterproofing on!- Updated 6/20/08
|
|
|
|
|
|
|
|
Radon Venting/ waterproofing in place.
|
|
|
|
ICFs after the pour. Photo courtesy of the homeowners
|
|
|
|
|
Pumping the walls- Photo courtesy of the homeowners
|
|
|
|
|
|
|
|
It has begun! Updated 6/07/08
Team Hybrid Member R-Value Concrete Structures is back to lead the ICF and Concrete work for us on the Vineyard Project. |
|
|
|
Another award winning combination!
This project will use BuildBlock ICFs. |
|
|
|
|
Footings
Here is a look at the footings for the Vineyard Project |
|
|
|
|
|
Proper house placement and site work.
|
|
|
|
|
|
Awesome location
|
|
|
|
|
This project is located next to a vineyard, thus the project name.
|
|
|
|
|