The Vineyard Project

Nestled in South Western Michigan's wine country, this Hybrid Home will be one to watch! The Vineyard Project is a Team Hybrid collaboration to be designed by Eric Hughes of Image Design and built by Adam Bearup of Hybrid Homes.

This home will incorporate alternative and renewable energy technologies and cutting edge products into its' ultra-high energy efficient shell!  We will do all this affordably so the homeowners will have money left to enjoy everything the house and area has to offer!

Updated 2/25/09 Concrete countertops are in!

Master closet shelves before painting

Lights over island

Tile shower water proofing

Hole for solar tube. See the insulation?!

Free light in pantry from solar tube light!

Installing concrete countertops. Made off site for a better quality

Farm Sink

Builtin book shelves

Custom french doors

Updated 12-22-08 Trim

Updated 11/11/08

Updated 10/26/08

Solar installation by Bauer Power

Stained concrete main floors!

Passive solar with the concrete main floors for thermal mass!

Re-inforced slab with radiant heat tubing in it for heat.

Concrete is stained in the concrete truck

Cedar porch

updated 9-12-08 Pouring the basement floor.

Colored concrete

Updated 8/27/08-Siding is on!

Installing in-floor heat tubing

A walk to remember- Updated 7/24/08

We got an incredible amount of work done this week!

On site chef. I believe that the crew works better when well fed. Here is one of our cooks.

This week was a blur, we hit 48 hours by Thursday night, so we loaded up our crews and got them home.

These pics will flow from completion backwards.

Roof being covered.

Looking at the project from the SkyTrack

Framing and sheathing

Finished setting trusses

Crane setting trusses.

You never know who is going to show up when you rent a crane out of town. We lucked out and set all the trusses in just over an hour!!

Setting a girder and mono trusses with the SkyTrack.

This weeks update is brought to you by Team Hybrid.

We built all of the interior walls

John hands a truss up to John.

Jeff readys the top plate so the girder truss would sit in the proper place.

Garage going up.

Laying out walls.- Updated 7/03/08

Setting floor joists.

Waterproofing on!- Updated 6/20/08

Radon Venting/ waterproofing in place.

ICFs after the pour. Photo courtesy of the homeowners

Pumping the walls- Photo courtesy of the homeowners

It has begun! Updated 6/07/08

Team Hybrid Member R-Value Concrete Structures is back to lead the ICF and Concrete work for us on the Vineyard Project.

Another award winning combination!

This project will use BuildBlock ICFs.

Footings

Here is a look at the footings for the Vineyard Project

Proper house placement and site work.

Awesome location

This project is located next to a vineyard, thus the project name.